 |
o June
2002 Reform Package [8L]
- Items
o Press release and talking points
o Report to the President
o Recommended Improvements to the NSR Program
- Rulemaking would be final for improvements previously proposed
and would be a proposal for new improvements
- Recommended improvements
o Plantwide applicability limits (PALs)
- Conduct final rulemaking allowing PALs based on actual emissions
(highest consecutive 24 month period within the immediately
preceding 10 years, taking into account the current emissions
factor (which would reflect emissions limitation and other
reductions since the baseline period) in combination with
the utilization level from the 24-month time period selected).
- Valid 10 years
- Source could make any change without triggering NSR as long
as actual emissions did not exceed PAL
- Renewal
" Emissions levels may be reevaluated by agency to determine
need for an adjustment
" Need can be based on air quality needs, advances in
technology and control cost effectiveness considerations
- PAL can be increased if criteria are met:
" Nonattainment area criteria: Opportunity for public
participation; modeling of increase as appropriate; application
of control technology to the changed or new emissions unit;
and securing necessary offsets.
" Attainment area criteria: Opportunity for public participation;
modeling the increase; apply control technology to the changed
or new emissions unit; and undertake any mitigation measures
that might be required.
- EPA plans to develop an alternative that would give a source
the option of obtaining a PAL based on allowable emissions.
o Clean Unit Exclusion
- Finalize the 1996 proposal
- Unit "clean" if underwent a review process that
resulted in BACT/LAER or equivalent (State minor NSR BACT)
within last 10-15 years from date the control was installed
or the project was implemented
- NSR triggered only if the permitted allowable emissions
are increased
- Inherently clean or lower emitting processes could also
qualify, as well as MACT and RACT if equivalent to BACT/LAER
o Pollution Control and Prevention Projects
- Finalize the 1996 proposal
- Would exclude from NSR the addition, replacement or use
at an existing emissions unit of any system, process, control
or device whose overall net impact on the environment is beneficial
(subject to certain conditions). The conditions are:
" Project cannot result in an emissions increase that
causes a violation of NAAQS or PSD increment, or result in
an adverse impact on Class I areas
" Complete replacement or reconstruction of an existing
emissions unit will not qualify for the exclusion
- EPA will provide a list of environmentally beneficial technologies
presumptively eligible for the exclusion, including:
" WEPCO rule list (40 CFR 52.21(b)(32)
" List in 1996 proposal
- Projects not on list must be determined environmentally
beneficial before such project can qualify for the exclusion
" Projects can qualify case-by-case
" Projects can be added to list
- Process
" Source provides prior notice to agency
" Source maintains records supporting source's determination
on site
" Source can seek determination from agency prior to
implementing the exclusion
o Actual to Projected Future Actual Methodology
- Finalize 1996 rulemaking
- Would apply to all industry sectors
- Used for all physical or operational changes except
" Addition of a new unit
" Complete replacement of an existing unit
- Source must keep on site records
" Supporting its determination and
" Of actual emissions for the following five years
- Actual emissions baseline
" For all sources except electric utility steam generating
units, actual emissions are based on the highest consecutive
24 month period within the immediately preceding 10 years,
calculated using the current emission factor and the utilization
level from the 24-month time period selected
" {Note: this is a combination of the current factor
and the past high utilization, so likely does not reflect
"true" actual emissions.}
- Future actual emissions calculation (causation link or "demand
growth" exclusion)
" Only emissions increases caused by a given change are
considered in measuring the emissions increase associated
with the change
" This means that EPA will apply the causation test in
the WEPCO rule and exclude from the calculation that portion
of the post-change emissions that both:
" (1) Could have been accommodated before the change
within the representative baseline period; and
" (2) Is attributable to an increase in projected capacity
utilization at the unit that is unrelated to the particular
change.
o Routine Maintenance, Repair and Replacement (RMR&R)
- EPA will propose cost-based thresholds using "well-established"
precedents from NSPS
- Projects whose aggregated costs are below the threshold
would automatically be considered RMR&R
- Projects whose aggregated costs exceed the threshold would
remain eligible for RMR&R treatment if they otherwise
qualify, without any presumption that they did not qualify
by virtue of their being outside the cost-based "safe
harbor"
- Two different provisions in the NSPS that could be used
" Reconstruction (50% or more of the cost of a new unit),
and
" Capital expenditure exclusion (projects below the "annual
asset guideline repair allowance" percentage thresholds
of 1.5 to 15%)
- These provisions would be adapted to operate in the NSR
context
" For example, annual dollar cost thresholds, average
on a rolling basis over a 5-year period (or some other period)
might be appropriate
" If the aggregate cost of maintenance expenses and capital
repair and replacement projects for the relevant unit do not
exceed the specified dollar threshold then the activities
would be deemed to be RMR&R and not subject to NSR
- The cost threshold would be set to cover RMR&R capital
and non-capital costs incurred to facilitate the safety, efficiency,
and reliability of the operation of the unit
" In the context of the NSPS, these would be set by reference
to historical invested basis
" However, for RMR&R, a more appropriate comparison
point might be capital replacement cost or another measure
that sets a consistent threshold for all facilities in a given
industry
" EPA would take comment on the most appropriate approach
- Excluded costs
" Any costs incurred for installing and maintaining pollution
control technology
" Also, EPA will consider excluding certain costs associated
with forced outages involving the unanticipated failure of
one or more major components
- Expenses beyond the safe harbor would not be presumed to
be non-routine (but could still otherwise qualify as RMR&R)
- Other considerations
" EPA may identify specific types of projects that cannot
be excluded from review by virtue of the thresholds
" However, EPA feels that the better approach may be
to utilize maximum achievable hourly emissions rate as the
mechanism for addressing this concern
- Definitional issues:
" EPA will propose that the replacement of existing equipment
with equipment that serves the same function and that does
not alter the basic design parameters of the unit (e.g., maximum
heat input and fuel consumption specifications for utilities)
typically would be considered RMR&R
" EPA will consider provisions identifying the types
of projects that are undertaken as RMR&R activities in
particular industrial sectors. Absence of a project from such
a list would not disqualify it from being considered RMR&R,
but would simply result in its being evaluated on a case-by-case
basis.
" For the utility sector, equipment that is maintained,
repaired and replaced can be categorized along functional
lines (e.g., boiler tube assemblies, air heaters, coal handling
equipment, pumps, etc.). Projects where the consequences of
delaying or foregoing the work could lead to lower availability
or the failure of the generating unit and create or add to
safety concerns would generally be considered routine, perhaps
using maintenance, repair and replacement activities identified
as common practice by the North American Electric Reliability
Council.
" Similarly, EPA could identify routine maintenance,
repair and replacement undertaken by refineries during turnarounds.
" Energy efficiency projects. EPA will affirm that existing
NSR rules are not intended to discourage activities that increase
efficiency and will propose that such improvements undertaken
through RMR&R activities will be considered RMR&R.
Energy efficiency projects will be considered routine IF the
improvements results from the replacement of existing equipment
with equipment that serves the same function and that does
not alter the original design parameters of the unit.
" EPA will take steps to "provide additional certainty
about RMR&R activities during the pendency of this rulemaking."
o Debottlenecking
- EPA will propose a clarification that, when calculating
actual emissions associated with a physical or operational
change, sources generally should look only at the unit undergoing
the change.
- Emissions from units upstream and downstream of the unit
being changed should be considered only when the permitted
emissions limit of the upstream or downstream unit would be
exceeded or increased as a result of the change.
o Aggregation
- EPA would propose clarification of its nonaggregation policy
by indicating that a project would be considered separate
and independent from any other project at a major stationary
source unless:
" The project is dependent upon another project to be
economically or technically viable, or
" The project is intentionally split from other projects
to avoid NSR.
- Also, EPA generally would defer to the States to implement
the Agency's aggregation rule.
|
|
Note:
To save the above mentioned
document "right click on the link then select Save
Target As," or "you can simply left click on the
link above in order to view the document."
|
|
 |
|